Highway: US 51 from Marathon County line to Lincoln County K (Exit 211) in Merrill
Schedule: Completion by Nov. 15
Project ID: 1176-22-72/73
Project description: Crews will remove the existing asphalt surface and crushed concrete and then replace them with base materials and asphalt pavement; complete minor grading at median crossovers for traffic control; repave maintenance crossovers and interchange ramps; and add additional guardrail on northbound US 51 at WIS 64.
Anticipated work scheduled: Crews will be adjusting and repairing guardrail along the southbound US 51 lanes.
Traffic impacts: Motorists can expect one lane of southbound US 51 to be closed from County K to the Wisconsin River from 6 a.m. Monday, July 11 to 6 p.m. Saturday, July 16.
Website: https://projects.511wi.gov/us51nbsb/
Highway: WIS 107 – Bridge over Little Pine Creek between Hillcrest and Dotter Roads
Schedule: June 15 to Aug. 17
Project ID: 9305-09-73
Project description: Crews will replace the existing structure with a bridge that will provide proper clear width and upgrade the existing guardrail to meet current standards.
Anticipated work scheduled: Crews will begin forming the floor of the box culvert, placing reinforcements and pouring concrete.
Traffic impacts: WIS 107 is closed to through traffic at Little Pine Creek, and traffic is being detoured via County J, US 51 and County S.