Lincoln County Construction Updates

Highway: US 51 from Marathon County line to Lincoln County K (Exit 211) in Merrill

Schedule: Completion by Nov. 15

Project ID: 1176-22-72/73

Project description: Crews will remove the existing asphalt surface and crushed concrete and then replace them with base materials and asphalt pavement; complete minor grading at median crossovers for traffic control; repave maintenance crossovers and interchange ramps; and add additional guardrail on northbound US 51 at WIS 64.

Anticipated work scheduled: Crews will be adjusting and repairing guardrail along the southbound US 51 lanes.

Traffic impacts: Motorists can expect one lane of southbound US 51 to be closed from County K to the Wisconsin River from 6 a.m. Monday, July 11 to 6 p.m. Saturday, July 16.

Website: https://projects.511wi.gov/us51nbsb/

Highway: WIS 107 – Bridge over Little Pine Creek between Hillcrest and Dotter Roads

Schedule: June 15 to Aug. 17

Project ID: 9305-09-73

Project description: Crews will replace the existing structure with a bridge that will provide proper clear width and upgrade the existing guardrail to meet current standards.

Anticipated work scheduled: Crews will begin forming the floor of the box culvert, placing reinforcements and pouring concrete.

Traffic impacts: WIS 107 is closed to through traffic at Little Pine Creek, and traffic is being detoured via County J, US 51 and County S.

Website: https://projects.511wi.gov/wis107littlepinecreek/